Merck &CO USA

Turnkey delivery of Swiss facility for Merck in six months

Project details

Client  
Merck & Co

 

Location  
Switzerland

 

Market  
Biologics / Process Technology Installations

 

Solutions we provided  
In-door modular facility for biotech High Containment dispensing

Turnkey delivery of Swiss facility for Merck in six months

With an accelerated timeline of just six months, KeyPlants was able to go from concept design to commissioning and qualification of MSD’s weighing and dispensing facility for high-containment biologics.

 

Merck chose us in part because we were able to meet the timeline. Built in 2012-2013, the 320 sqm modular expansion of their Swiss facility was the first one designed and built using our innovative indoor box-in-box system.

 

Scope: Basic design, fabrication, integration of process equipment, assembly.

 

Major drivers: Speed

 

Objective: Turnkey delivery of the facility through off-site construction within 6 months

Do you have any questions?

Do you have any questions?