Turnkey delivery of Swiss facility for Merck in six months
Project details
Project details
Client
Merck & Co
Location
Switzerland
Market
Biologics / Process Technology Installations
Solutions we provided
In-door modular facility for biotech High Containment dispensing
Turnkey delivery of Swiss facility for Merck in six months
Turnkey delivery of Swiss facility for Merck in six months
With an accelerated timeline of just six months, KeyPlants was able to go from concept design to commissioning and qualification of MSD’s weighing and dispensing facility for high-containment biologics.
Merck chose us in part because we were able to meet the timeline. Built in 2012-2013, the 320 sqm modular expansion of their Swiss facility was the first one designed and built using our innovative indoor box-in-box system.
Scope: Basic design, fabrication, integration of process equipment, assembly.
Major drivers: Speed
Objective: Turnkey delivery of the facility through off-site construction within 6 months